Properties Overview
There are two types of work schedules: company and employee. Company schedules define standard work and non-work days and company holidays. Employee schedules derive from company schedules but may include modifications that reflect the employee’s personal schedule.
If no modifications have been made to an employee’s work schedule, the properties match those defined in the company work schedule.
Work schedule modifications that are specific to one employee or a group of employees are made in either the Edit Day subtask or the Edit Daily Schedule subtask.
When you select a date from the Month/Year table (for example, March 10th) and make changes in the Edit Day subtask, any modification you make, such as changing it to a non-workday, applies only to that single date.
By contrast, when you modify the properties of a recurring day of the week (for example, Wednesday) in the Edit Daily Schedule subtask, the changes are applied to that day in both the current week and all future weeks.